School refurbishment feasibility study brief

Authored by Oliver Wakefield-Smith, Founder of Digital Signet. Working from RIBA Plan of Work 2020, RICS NRM1, BB103/BB104 and ESFA CIF 2026-27 rules.

Refurbishment feasibility on an occupied site is dominated by phasing logic: how to keep the school open while strip-out, asbestos removal and re-services work proceeds. The risk register earns its keep.

Whole-school refurbishment scope

Condition survey (refreshed), R&D2 asbestos survey, M&E adequacy report, options appraisal (full refurb vs phased refurb vs partial-replace), occupied-site phasing strategy, Cost Plan A, planning impact assessment, full risk register.

Occupied-site phasing

Phasing is the single biggest fee driver. A three-phase plan with summer-holiday peaks is the common shape; the brief must require the consultant to model curriculum impact, decant space and parent-communications burden.

Asbestos and R&D2

HSG264 R&D2 survey is mandatory before any intrusive works [source: HSE HSG264, verified 2026-06-24]. The brief must commission a refresh of the asbestos register and an R&D2 plan; budget £4,000-£12,000 for the survey itself depending on building age and area.

Typical fee envelope

Stage 0-2 multidisciplinary for a 1980s secondary refurb commonly £25,000-£42,500. Phasing complexity at the upper end.

Funding route

CIF is the primary route for individual building elements (roof, windows, boiler). SCA is the route for large MAT block refurbishment programmes managed in-house [source: SCA 2025-26, verified 2026-06-24].

Last reviewed against CIF 2026-27 round, RIBA POW 2020 and BB103/BB104 on 24 June 2026.